Below is an example.
PROJECT STATUS REPORT
CLIENT: Mr and Mrs Jones. CLIENT PHONE: 407-xxx-4729
PROJECT: Lot 12 Sunset Bay WEEK ENDING: December 24, 2014
ANTICIPATED COMPLETION DATE: March 28, 2015
REVISED COMPLETION DATE:
WORK COMPLETED THIS WEEK:
Meet pool company on site, continue site grading, install septic system tanks, ceramic tile continued, complete bonus room cabinet installation, continue interior trim, install window sills, delivery of bath vanities, delivery of dining room ceiling medallion, water test exterior windows and doors, site clean up, order precast concrete materials, fabricate cabinet in wine room.
WORK IN PROGRESS: Floor & wall tile, interior trim, counter tops, septic
WORK SCHEDULED FOR NEXT WEEK:
Install crown molding on 2nd floor, starting treads and wall cap installed, stone in exterior recesses, install kitchen counter top, trim plumbing start, ceramic tile continued, trim carpentry continued, install septic drip system, install concrete for gate columns, Client delivery of foyer ceiling medallion, install wine room top.
________________________________________________________________________________________
INFORMATION NEEDED FROM CLIENT:
Waiting for Client decision on Study built in REQUESTED: 12/17/14
Waiting for Client approval of front door REQUESTED: 12/10/14
ON / AHEAD / BEHIND SCHEDULE: (REASON)
_______________________________________________________________________________________
THIS INFORMATION IS BEING PROVIDED IN AN EFFORT TO KEEP YOU BETTER INFORMED WITH THE STATUS OF YOUR HOME. IF YOU HAVE ANY QUESTIONS OR CONCERNS, PLEASE CALL US AT 407-539-xxxx.
REGAL CLASSIC HOMES ON SITE MANAGER: MICHAEL MCGUFFIE
No comments:
Post a Comment